Benaka has been awarded a $16.8 million firm-fixed-price contract for construction of an F-16 mission training center facility in Egg Harbor Township, New Jersey.
The project will provide dedicated infrastructure supporting F-16 training activities and is expected to be completed by January 31, 2028.
The contract was awarded following an internet solicitation that generated eight bids.
At the time of the award, the government obligated the full $16.8 million contract amount using fiscal 2025 military construction, Army funding.
The U.S. Property and Fiscal Office for New Jersey is the contracting activity under contract W50S8F-27-C-A010.
Mission training centers provide facilities where aircrews and supporting personnel can conduct simulator-based training and prepare for operational scenarios in controlled environments.
For F-16 units, simulation infrastructure can allow pilots to rehearse missions, practice tactics, and maintain readiness without requiring every training event to involve an actual aircraft sortie.
The new facility in Egg Harbor Township will add infrastructure supporting those training requirements in New Jersey.
Simulator-based training can also reduce aircraft operating demands while allowing units to conduct complex exercises that could otherwise require significant airspace, fuel, maintenance, and logistical resources.
The project is structured as a firm-fixed-price agreement, meaning Benaka will complete the defined construction scope at the agreed contract price.
The eight bids received indicate the project was competitively procured.
Construction is expected to continue through early 2028.
The award represents another investment in infrastructure supporting the F-16, which continues to serve as an important fighter platform within U.S. and allied military aviation.
A dedicated mission training center can support both individual pilot proficiency and more complex collective training scenarios.
It can also provide units with additional flexibility to conduct training when aircraft availability, weather, or airspace limitations make live flying more difficult.
The full $16.8 million contract amount was obligated at award, providing the funding needed to move the construction program forward toward its January 2028 completion target.