Clark Construction Group has received a $9.47 million modification to its U.S. Army Corps of Engineers contract for design-build construction of a Department of Veterans Affairs health care center at Fort Bliss, Texas.
The latest modification increases the total cumulative face value of the contract to approximately $629.87 million.
The additional $9.47 million is being funded with fiscal 2024 Department of Veterans Affairs construction appropriations.
The full modification amount was obligated at the time of the award.
Work will continue at Fort Bliss, Texas, where the health care center is being constructed.
The Army currently estimates project completion by December 27, 2027.
The U.S. Army Corps of Engineers’ Fort Worth District is the contracting activity.
The award is modification P00016 to contract W9126G-24-C-0004.
The underlying contract uses a design-build model, which places design and construction responsibility within an integrated project structure rather than procuring those functions through completely separate contracts.
The latest action represents an incremental increase to a project with a cumulative value exceeding $629 million.
The Fort Bliss work supports Department of Veterans Affairs health care infrastructure serving veterans in the region.
Although the modification itself is valued below $10 million, the overall contract represents a major federal construction program.
Clark Construction is also among the companies participating in the separate NAVFAC Southwest multiple-award construction contract that received a combined $99 million ceiling increase.